A clear site guide for project teams. All work must follow the approved drawing, method statement, safety procedure and project specification.

Approved drawing, soil report, fault-current study, BOQ, datasheet and inspection plan.
Electrode, EBF compound, chamber, conductor, clamps/test link, labels and test instruments.
Confirm accessibility, separation, routing and absence of buried utilities before excavation.
Confirm the approved location, soil conditions, access, underground services and installation constraints.
Prepare the pit/bore to the depth and diameter shown on the approved design. Keep excavated material controlled and the area barricaded.
Place the selected electrode vertically and centrally. Protect the terminal and prevent damage to coatings or connections.
Place EBF compound uniformly around the electrode according to the approved method and manufacturer’s instructions. Avoid voids and contamination.
Connect the specified earthing conductor using compatible hardware. Ensure clean contact surfaces, correct tightening and corrosion protection.
Install the chamber so that the test point remains safe, labelled, accessible and protected from traffic or water ingress as required.
Carry out visual inspection, continuity checks and earth-resistance testing using the approved test method and calibrated instrument.
Record location, model, dimensions, conductor details, test readings, instrument ID, date, weather/soil conditions and photographs.
The drawing is schematic only. Depth, bore diameter, conductor size, chamber rating, spacing and backfill quantity must be taken from the approved project design.
| Location | Matches approved drawing and is safely accessible. |
|---|---|
| Electrode | Correct model, material, dimensions and undamaged condition verified. |
| Connection | Compatible clamp/test link, secure termination and conductor identification. |
| Chamber | Correct level, cover rating, drainage/protection and clear access. |
| Test result | Measured using the approved method and compared with the project acceptance criterion. |
| Records | Photos, test sheet, instrument calibration details and as-built location captured. |
Check chamber condition, labelling, conductor integrity, corrosion and loose connections at the project-defined interval.
Retest according to the maintenance plan and after major electrical, civil or environmental changes.
Investigate abnormal readings through site assessment and approved engineering review rather than adding water or chemicals without authorisation.