A professional field sequence for contractors, EPC teams, consultants and inspection personnel.

Approved drawing, BOQ, datasheet, soil report, method statement and ITP.
Permits, service detection, barricading, PPE, isolation and competent supervision.
Electrode, EBF, chamber, conductor, clamps, labels and calibrated test instruments.
Confirm approved point, access and underground services.
Follow approved depth, diameter and excavation controls.
Keep vertical and central; protect coating and terminal.
Place uniformly and avoid voids, foreign material and segregation.
Use compatible hardware and secure testable termination.
Ensure safe level, access, identification and mechanical protection.
Check continuity and earth resistance with calibrated equipment.
Submit photos, as-built data, readings and inspection documents.
| Location | Matches the approved drawing and remains accessible. |
|---|---|
| Electrode | Correct model, construction, size and undamaged condition verified. |
| Connection | Correct conductor, compatible clamp/test link and protected joint. |
| Inspection chamber | Correct level, cover rating, access and identification. |
| Testing | Approved method, calibrated instrument and traceable readings. |
| Documentation | As-built location, photographs, inspection sheet and test certificate. |